Howard Hughes Merriweather Parking Structure


The Shockey Precast Group was contracted by general contractor Harvey Cleary to design, manufacture, and erect the 378,848 SF Howard Hughes Merriweather Parking Structure in Columbia, Maryland. This project offered several interesting design and erection challenges, including coordinating site access and precast erection to accommodate the adjacent office building construction site, which was located only 30 feet from the parking structure construction site. For the nine-level parking structure with eight suspended precast levels, SPG produced and erected a total of 346,276 SF of precast. SPG began erection of the precast on March 30, 2016 and completed on July 5, 2016, three-and-a-half weeks early.

Project Details

  • Name Howard Hughes Merriweather Parking Structure
  • Location Columbia, Maryland
  • Owner HRD Development Management
  • Architect Design Collective
  • General Contractor Harvey-Cleary Builders
  • Size 378,848 SF